Comstock Production Licence Granted
Released
Released
Announcement PDF
Aureka Limited | ACN 125 140 105
Level 30, 35 Collins St, Melbourne VIC 3000
www.aureka.com.au
5 November 2026
ASX Market Release
PRODUCTION LICENCE GRANTED
ST ARNAUD – COMSTOCK GOLD & SILVER PROJECT
HIGHLIGHTS
• Aureka has had its small mining licence (“Prospecting Licence” PL008915) granted for the Comstock
Gold & Silver Project at St Arnaud.
• The production licence covers approximately 4.5 hectares within the previously disturbed Comstock
mine site, including the Walkers Zone and the main Comstock Shear to the south. Aureka’s 100% owned
Wedderburn Gold Processing Mill, 45km away, is the planned offsite processing route for Comstock.
• This positive approval decision from Resources Victoria has taken less than 4 months since application
acceptance. Aureka sees this as a signal Victoria is positively supporting responsible industry. Aureka
will now begin next steps to bring mining back to the St Arnaud Comstock area, last seen in 1995. This
includes resource definition, mine design, Work Plan approval and stakeholder consultation.
PATHWAY GRANTED FOR MINING TO RETURN TO COMSTOCK
Aureka Limited (ASX: AKA) (Aureka or the Company) is pleased to announce that Prospecting Licence
PL008915 has been granted over the Company’s Comstock Gold & Silver Project, approximately 2km
north-northwest of St Arnaud, Victoria, on 4 of November 2026. The licence was granted by Resources
Victoria, and the decision was delivered within a prompt 4-month timeframe from application
acceptance.
The application for PL008915 was lodged by North Central Gold Exploration Pty Ltd, a wholly owned
subsidiary of Aureka. The application was submitted on 1 July 20261
and was accepted by the regulator
on 16 July 2026, from which date it took effect. The proposed program of work is small scale selective
underground mining, shallow excavations and rehabilitation focused at the southern end of the pit.1
The licence covers approximately 4.5 hectares, including the Walkers Zone and the main Comstock Shear
the target areas for mining within the licence area. The licence area is located entirely within the
previously disturbed Comstock mine site (refer Figure 1 and Appendix A). The licence was applied for and
granted for a term of 7 years.
A Prospecting Licence supports smaller scale operations of limited life of up to 7 years (no extensions)
and could be superseded by a conventional Mining Licence if future geological work supports this.
ASX Announcement | 5 November 2026
Page 2
Managing Director, James Gurry, said:
“Securing our first production licence is an important milestone for Aureka. When we started out, St Arnaud
Comstock was an old pit in a small part of a much larger exploration licence. Since then we published the 56koz
inferred Comstock JORC Resource in June 2025, subsequently ran multiple drill campaigns intercepting
numerous instances of visible and high-grade gold and silver including up to 109g/t returned from Comstock.
The 109g/t Au sits within a broader 1m @ 65.37g/t Au from 116.2m in hole 25NED002, first reported in our ASX
release on 20 November 2025 ‘St Arnaud Comstock – High Grade Assays’8
, and then applied for this licence to
path the way to restart production at Comstock, last seen here in 1995.
In my view the licence granted in under 4 months is another sign Victoria is emerging as a jurisdiction that
genuinely supports responsible industry.
We intend to operate Comstock alongside the already producing Fiddlers Creek underground mine, both mines
feeding into the Wedderburn Gold Processing Mill, thereby maximising synergy between operations. Our focus
over coming months is integration, production optimisation and realising free cash from Fiddlers Creek - while
in parallel - taking the next pre-development steps to turn Comstock once again into production reality thanks
to this licence approval.”
Chief Operating Officer, Zane Smith, said:
“We wish to thank Resources Victoria, Parks Victoria, Djaara and the local community for their cooperation in
getting Comstock to this important point. With the licence granted, our focus turns to resource definition,
metallurgical studies, site readiness, and the consent and engagement requirements that apply before any work
starts. The processing pathway through our Wedderburn Mill is well established in terms of capacity and we
will assess any minor mill flow sheet modifications required for Comstock ore. The existing access and
previously disturbed footprint across the Walkers and Comstock areas give us a practical starting point, and
we will complete the remaining work required before any decision to mine.”
Licence Conditions
The licence is subject to the standard conditions of grant – e.g. approved work plan, rehabilitation bond
and other standard conditions for a planned mining operation under a Prospecting Licence in Victoria.
The licence area is entirely within Crown Land within the St Arnaud Regional Park, therefore consent of
the Crown Land Minister, through Parks Victoria, is required before works commence. The licence is also
subject to the Djaara (Dja Dja Wurrung Clans Aboriginal Corporation) Land Use Activity Agreement,
including its consultation and notification requirements. The grant of the licence does not constitute a
decision to commence mining, and Aureka has not made a decision to mine at Comstock.
ASX Announcement | 5 November 2026
Page 3
Figure 1: Comstock Gold & Silver Project – potential site layout within the previously disturbed Comstock mine site. The
Prospecting Licence PL008915 boundary is indicated with the red line, covers less than 5 hectares and is entirely within the
previously disturbed mine site area.
ORE PROCESSING PLANNED AT THE WEDDERBURN MILL
Comstock is planned as an offsite processing operation, with ore to be processed at the Wedderburn
Gold Processing Mill, located approximately 45km from Comstock. Wedderburn has ample spare
capacity to process both increased production from Fiddlers Creek and ore from Comstock (if and when
production commences). Comstock ore will now be subject to metallurgical testing building upon the
historical processing records that exist for the site.
NEXT STEPS
While Aureka focused on maximising production and the operations of the Fiddlers Creek underground
mine, the next steps for Comstock include obtaining Parks Victoria and Crown Land Minister consent,
engaging with the Djaara (Dja Dja Wurrung Clans Aboriginal Corporation) and the local community.
Aureka will also be developing operating procedures to meet the Land Use Activity Agreement conditions
before any site work starts over the next three to months. Metallurgical testing and further exploration
are also planned.
ASX Announcement | 5 November 2026
Page 4
Figure 2 – Images from the Wedderburn Gold Processing Mill, the nominated site for processing of ore from Comstock Gold & Silver Project
45km away and where ample current spare capacity exists.
Figure 3 – View of the high-accuracy LiDAR and photogrammetry of the Comstock open-cut pit – looking towards the South (azimuth
18).
ASX Announcement | 5 November 2026
Page 5
COMMUNITY AND STAKEHOLDER CONSULTATION
The licence area is Crown land within the St Arnaud Regional Park and is subject to the Djaara Land Use
Activity Agreement. Before any site work begins, Aureka will obtain the consent of the Crown Land
Minister through Parks Victoria and will engage with the Djaara (Dja Dja Wurrung Clans Aboriginal
Corporation) in accordance with the agreement. This includes ongoing consultation, keeping Djarara
informed of project progress. Aureka will also engage with the St Arnaud community, neighbouring
landholders and other stakeholders as the project progresses.
COMSTOCK MINERAL RESOURCE AND EXPLORATION TARGET
In June 2025 Aureka released a maiden JORC Mineral Resource Estimate (MRE) for Comstock of 1.45Mt
at 1.21g/t Au for 56,500oz of gold (Table 1).2
An Exploration Target around the Inferred Resource was
also estimated to range between 3.0Mt and 3.5Mt at grades of 1.2g/t to 1.0g/t gold, for an Exploration
Target range of 112koz to 116koz of gold, and potentially economic amounts of silver at grades of 1.9g/t
to 2.02g/t Ag, for a total of 195koz to 214koz of silver (Table 2).2
Cautionary statement: The potential quantity and grade of the Exploration Target set out in Table 2 is
conceptual in nature and was reported in 2025 for St Arnaud.2
There has been insufficient exploration to
estimate a Mineral Resource, and it is uncertain if further exploration will result in the estimation of a
Mineral Resource. The Exploration Target has been prepared and reported in accordance with the 2012
edition of the JORC Code.
Table 1 – Comstock Project Mineral Resource Estimate in accordance with the 2012 edition of the JORC Code.2
Prospect
Cut-Off
Gold
(g/t)
Inferred
Tonnes Gold Grade
(g/t)
Gold
Ounces
Grade
(g/t)
silver
Silver
(oz)
Comstock
(St Arnaud)
>0.5 1,450,000 1.21 56,500 2.14 100,000
The preceding statement of Mineral Resources conforms to the Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves (JORC Code) 2012 Edition. All tonnages reported are dry metric tonnes. Minor discrepancies may
occur due to rounding to appropriate significant figures.
ASX Announcement | 5 November 2026
Page 6
Table 2 – Comstock Project estimated Exploration Target in accordance with the 2012 edition of the JORC Code.2
Prospect
Exploration Target*
Range Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
ounces (k
Oz)
Silver
Grade
(g/t)
Silver
ounces (k
Oz)
Comstock
(St Arnaud)
Lower 3.0 1.2 116 2.02 195
Upper 3.5 1.0 112 1.90 214
*The potential quantity and grade of the Exploration Target is conceptual in nature and there has been insufficient exploration
to estimate a Mineral Resource in relation to this Exploration Target. It is uncertain if further exploration will result in the
estimation of a Mineral Resource in relation to these Exploration Targets.
COMSTOCK PROJECT BACKGROUND
The Comstock Gold & Silver Project is located near St Arnaud, Victoria, and hosts a JORC Inferred Mineral
Resource of 1.5Mt for 56koz of gold.2
The Comstock pit and surrounding area is a previously mined and
disturbed site, with road and pit ramp access last used in the late 1990s.3
ASX Announcement | 5 November 2026
Page 7
Figure 4: Location of the Comstock Project (circled in blue) on the Nelson line of reef within the St Arnaud Gold Project. The St
Arnaud goldfield historically produced approximately 400koz at 15g/t Au.11
ASX Announcement | 5 November 2026
Page 8
Figure 5: St Arnaud Comstock pit, looking SE.
Historical mining in the area dates to the mid-1800s, and the Comstock and Walkers pit were previously
mined from 1992 to 1995 by Glenburn Manor (International Minerals NL) extracting ~8,000 ounces of
gold11
.
Comstock lies on the Nelson line of reef, approximately 2km north of the St Arnaud township, within a
wider goldfield that historically produced approximately 400koz at an estimated 15g/t Au.11
Modern
exploration at Comstock has been carried out by a succession of explorers since the late 1970s, including
Carpentaria Exploration (1979–1981), Sanidine NL (1982–1986), Compass Resources (1987–1994), CRA
(1994–1996), Planet Resources (1995), Rex Minerals (2007–2009), Oxiana (2007), Goldfields Australia
(2008–2009), Bora Bora Resources (2012–2018) and Navarre Minerals (2018–2021). Aureka has been
exploring the project since 2025.8
Primary gold mineralisation at St Arnaud is hosted in structurally controlled quartz veins associated with
folding and NNW-trending, west-dipping thrust faults. The reefs can extend from a few metres to a few
kilometres along strike, though usually a few hundred metres, and have steeply plunging gold shoots.
The mineralisation has a base metal signature of Au + As + Ag + Pb, and historical records describe the
gold ore as having a relatively high sulphide content of up to 5% (pyrite, chalcopyrite, arsenopyrite,
galena). Most historical mines stopped at the oxide–sulphide interface because of reduced grade and
poorer recoveries from sulphide ores, and higher gold values appear to be associated with green-black
carbonaceous shales.8
The Comstock pit lies wholly on Crown land. A 2,253m diamond drilling program completed in September
2025 by Aureka targeted potential extensions to known mineral trends, along strike and down plunge,
within 100m of the Mineral Resource and previous drilling.8
ASX Announcement | 5 November 2026
Page 9
An initial Concept Study completed by Measured Group Pty Ltd and Minserve Pty Ltd, with input from
Core Prospecting Pty Ltd, identified on a conceptual basis a potentially efficient mining pathway at
Comstock involving modest pre-production capital cost. This capital relating primarily to onsite set up
and site overheads rather than extensive earthworks and pre-mine development.1
This Concept Study
was published in 2026, and is not a Scoping Study, Pre-Feasibility Study or Feasibility Study under the
JORC Code 2012.
The 2026 Comstock and Walkers pits have been subject to infill diamond drilling, focused on the Walkers
Zone and the southern extensions of the Comstock Shear. The program aims to validate historical drilling
data, increase drill data density to potentially support a higher confidence classification for a portion of
the Inferred Mineral Resource, and provide samples for metallurgical testing.3
Figure 6: St Arnaud Comstock – Long section with significant mineral intercepts. Green callout – results first reported in the ASX
release of 25 August 2026;8
brown callout – previous significant intercepts. Previous result details: ASX Release, 22 Dec 2025: St
Arnaud Comstock – Shallow Visible Gold in New Structure; all other previous results: ASX Release, 13 June 2025: St Arnaud
Maiden JORC MRE and Exploration Target – Amended.2
HIGH GRADE DRILLING IN 2026
Diamond drilling at Comstock and Walkers has returned high-grade gold and silver intercepts on both
lines of reef – the Walkers Zone and the main Comstock Shear – with mineralisation now extending to
the south. The results below were first reported in the Company’s ASX release of 25 August 20268
, which
includes the key assay data and the JORC Code, 2012 Edition, Table 1, and are re-presented here in
ASX Announcement | 5 November 2026
Page 10
summary. All intercepts are down hole widths; estimated true widths are interpreted to represent
between 50% and 80% of down hole widths.
• Comstock Shear – NED032: 4.4m @ 8.9g/t Au and 57.8g/t Ag from 102.8m, including 0.3m @ 65.3g/t
Au from 106.2m (duplicate returning 95.6g/t Au).
• Walkers Zone – NED035: 2.65m @ 5.78g/t Au from 20.5m (including previously sighted visible gold9
),
including 0.35m @ 34.2g/t Au from 21.5m.
• Walkers Zone – NED033: 0.3m @ 21.3g/t Au from 35.6m, and 1.9m @ 5.63g/t Au from 56.5m,
including 0.9m @ 11.1g/t Au from 56.5m.
The NED032 intercept on the Comstock Shear is only 48m below the surface of the southern portion of
the main Comstock pit, where historically very limited exploration drilling has been conducted, and is
within the Prospecting Licence area. The shallow high-grade results in the Walkers Zone are consistent
with legacy drilling results from the 1980s and 1990s.
These results, combined with the 2025 Comstock diamond drilling conducted by Aureka, will be
incorporated into a future JORC estimate review of the Comstock Project and aim to build upon the
current JORC Inferred Mineral Resource Estimate of 56koz of gold.2
The grade tenor and lack of significant
sulphides suggest the mineralisation may be free milling gold, which is to be confirmed by a metallurgical
testing program.
Figure 7: St Arnaud Walkers – Long section with significant mineral intercepts. Green callout – results first reported in the ASX
release of 25 August 2026;8
brown callout – previous significant intercepts. Previous result details: ASX Release, 22 Dec 2025: St
Arnaud Comstock – Shallow Visible Gold in New Structure; all other previous results: ASX Release, 13 June 2025: St Arnaud
Maiden JORC MRE and Exploration Target – Amended.2
ASX Announcement | 5 November 2026
Page 11
Figure 8: St Arnaud Comstock – Plan view of the Comstock pit with location of the mineral intercepts. Intercepts labelled as new
significant intercepts were first reported in the ASX release of 25 August 2026.8
ASX Announcement | 5 November 2026
Page 12
AUREKA’S PORTFOLIO OF COMPLEMENTARY ASSETS
Aureka is an integrated Victorian gold company encompassing current production, near term
development and large-scale growth projects, as well as regional exploration opportunity.
Aureka’s Inferred JORC Mineral Resources total approximately 455koz @ 2.27g/t Au. The flagship Irvine
Project has a JORC Inferred Mineral Resource of 398koz,6
and is located 16km from the operating Stawell
Gold Mine that has a production history of over 5Moz.7
The Fiddlers Creek Underground Gold & Silver mine re-started production in 2025 as a high-grade smaller
scale operation. To the north lies the St Arnaud Comstock Gold & Silver Project with a JORC Inferred
Mineral Resource of 56koz grading 1.21g/t gold2
in a pit previously mined until 1995 and with
Prospecting Licence PL008915 granted on 4 November 20261
Aureka’s 100% owned Wedderburn Gold Processing Mill is one of a limited number of gold mills in
Victoria, currently processes ore from Fiddlers Creek and has stated spare capacity.
Aureka’s tenement package also includes the Jubilee Gold Exploration Project near Ballarat, Morning Bill
Gold and Base Metals Project on the Stavely Volcanics (Stawell Corridor), and critical minerals potential
in the greater St Arnaud area.
Figure 9: Plan view of Victoria including Aureka’s key projects with respect to the major nearby towns, cities and projects
ASX Announcement | 5 November 2026
Page 13
Figure 10: St Arnaud Comstock Project relative location to a number of gold processing mills in Victoria, including Wedderburn
within the 50km range.
ASX Announcement | 5 November 2026
Page 14
IMPORTANT INFORMATION
The Comstock Mineral Resource is 100% classified as Inferred. Further infill drilling and reporting in
accordance with the JORC Code is required before there would be reasonable grounds for publishing a
compliant Production Target and scenario financial outcomes. Grant of the Prospecting Licence does not
mean that mining will occur or that any operation will be economic. The Concept Study does not meet
the requirements of a Scoping Study under the JORC Code, is not sufficient to support the estimation of
Ore Reserves, a Production Target or forecast financial information, and there is no assurance that its
conceptual findings will be realised. Aureka will require additional funding to progress Comstock, and
there is no certainty that funding will be available when needed or on terms that are not dilutive to
existing shareholders.
The Company confirms that it is not aware of any new information or data that materially affects the
information included in the relevant announcement and that all material assumptions and technical
parameters underpinning the estimates in the relevant announcement and that all material assumptions
and technical parameters underpinning the estimates in the relevant ASX announcement continue to
apply and have not materially changed.
Competent Persons Statements
The information in this announcement that relates to exploration results, data quality and geological
interpretation, is based on, and fairly represents, information compiled by Jozef Story, a Competent
Person who is a Member of the Australian Institute of Geoscientists (MAIG) (#10079). Jozef has sufficient
experience that is relevant to the style of mineralisation and type of deposits under consideration and to
the activity currently being undertaken to qualify as a Competent Person as defined in the 2012 Edition
of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves.’ Jozef
consents to the publishing of the information in this presentation in the form and context in which it
appears. Jozef is employed by Aureka.
The information in this announcement that relates to Mineral Resources and Exploration Target
statements is based on, and fairly represents, information compiled by Daniel Brost BSc (Economic
Geology) – MSc (Mine Engineering). D Brost is not employed by Aureka and has acted as an independent
consultant on the Comstock Prospect Mineral Resource estimation. D Brost is a Chartered Professional
Geologist and a Member of the Australasian Institute of Geologists (MAIG) (#221836) and has sufficient
experience with the style of mineralisation, the deposit type under consideration and the activities
undertaken to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code
for Reporting of Exploration Results, Mineral Resources and Ore Reserves” (the JORC Code). D Brost
consents to the inclusion in this announcement of the contained technical information relating to the
Mineral Resource estimation in the form and context in which it appears.
This announcement has been approved for release by the Board.
For further information, please contact:
James Gurry
Managing Director
James.Gurry@aureka.com.au
+61 451 349 688
David Waterhouse
Investor Relations
ir@aureka.com.au
+61 407 880 937
ASX Announcement | 5 November 2026
Page 15
Footnote reference Table
1 ASX Release 1 July 2026: Comstock Study Update – Walkers Pit Selected / Licencing Submitted
2 ASX Release 13 Jun 2025: St Arnaud Maiden JORC MRE and Exploration Target – Amended.
3 ASX Release 29 May 2026: Infill drilling commences at Comstock
4 ASX Release 14 July 2026: Toll Milling Agreement Signed for Wedderburn Gold Mill
5 ASX Release 7 Sept 2026: Victorian mine and mill acquisition - Placement and SPP
6 ASX Release 18 June 2026: Global JORC Resource Increase to over 450koz
7 11 Nov 2024 Stawell Gold Corridor Conference Presentation: Stawell-gold-corridor-conference-stawell-gold-mines-271124.pdf
8 ASX Release 25 August 2026: St Arnaud – Comstock Project Update – High Grade Gold Intercepts on Both Comstock and Walkers
9 ASX Release 11 August 2026: Comstock – Multiple Visible Gold Intercepts on Walkers Zone
10 Notice of Application for a Prospecting Licence PL008915, St Arnaud (North Central Herald advertisement)
11 St Arnaud historical production taken from: Krokowski de Vickerod, J., Moore, D.H. and Cayley, R.A., 1997.
ASX Announcement | 5 November 2026
Page 16
APPENDIX A – PROSPECTING LICENCE PL008915
•
Figure 11: Prospecting Licence PL008915 area in relation to Crown land (1:25,000 scale). Source: Department of Energy,
Environment, and Climate Action / Resources Victoria – 4 November 2026.