Quarterly Activities Report and Appendix 5B
Released
Released
Announcement PDF
A S X A N N O U N C E M E N T
30 July 2026
ASX Market Release
Quarterly Activities Report and Appendix 5B
Highlights
• Global JORC Resource Increase by 26% to 455koz from 361koz of gold1
. This is a 50% increase in
global JORC Resources since the start of Aureka’s drilling activities in January 2025. JORC Resource
increase driven by the flagship Irvine Gold Project in the Stawell Corridor where the 100% Inferred
JORC Compliant Resource increased by 30% to 398koz of inferred gold.
• Updated Exploration Targets at the Irvine Gold Project were reported including Advanced Targets
57koz – 130koz gold, and conceptual Exploration Targets 151koz – 348koz gold.
• Irvine Project – High Resolution Magnetic Drone Survey Identified New High Priority
Targets2
. Preliminary interpretation of the data informed the revised Exploration Targets
identifying several new key areas of interest featuring emerging structural complexity outside the
Inferred Mineral Resource.
• St Arnaud Comstock Project – Infill Drilling Commenced3
, with diamond drilling aiming to infill
and reaffirm legacy drilling completed within the Walkers sub-pit of the main Comstock pit.
• Cash at end of quarter: $2.3m.
• Subsequent to quarter end: Aureka confirmed Walkers Pit at Comstock as targeted first
production and applied for a production licence (PL008915). A binding toll mill partnership with
the Wedderburn Gold Processing facility was announced on 14 July. COO Zane Smith was
appointed on 28 July.
• Current activities: Two diamond drill rigs currently in operation, exploring highly prospective
opportunities at the Irvine Gold and the Comstock Gold & Silver Projects. Drilling at Irvine continues
to explore both immediately along strike of the Resolution Resource area as well as step change
targets distal from the known mineralised lodes; while at St Arnaud drilling is ongoing within the
Comstock Walkers pit infilling and reaffirming legacy drilling as the Company looks towards
near-term low tonnage mining opportunities. Drilling programs are supported by updated
geological models, anomalous geochemistry and favourable geophysical responses and aim to
generate further growth to the 455koz global Inferred gold resources.
James Gurry, Managing Director, said: “June was another significant quarter of achievement for Aureka
with the increase to global Inferred JORC gold Resources to 455koz, commencement of infill drilling at Comstock
and just after quarter’s end - applying for our first production licence and signing of a milling partnership giving
our ore a pathway to market – these latter steps should not be underestimated for their significance. I’d like to
thank the team for their dedication to delivery this past quarter.”
1
ASX Release 18 June 2026: Global JORC Resource Increase to over 450KOZ
2
ASX Release 05 June 2026: MAG Survey Identifies New High Priority Targets
3
ASX Release 29 May 2026: Infill Drilling Commences at Comstock
30 JULY 2026
ASX : AKA B R I N G I N G V I C T O R I A ' S G O L D T O L I F E 2
30 JULY 2026
Ongoing exploration strategy delivers 26% increase to Global JORC resource
during June Quarter
Aureka Limited (ASX: AKA) continues to advance its gold exploration projects in Victoria with ongoing
drilling activities and detailed interpretation of newly acquired geophysical datasets resulting in a
significant increase in the Company’s global resources from 361koz of gold in Inferred Resources to
455koz4
, primarily from the flagship Irvine Project where 94koz of additional gold was added during the
quarter5
.
An improved geological understanding, new geological domains and the successful diamond drilling by
Aureka commencing in 2025 combined to drive the revision in the JORC Resource and Exploration
Target at the Irvine Gold Project. The increase is attributable to the Resolution Lode, including the
high-grade Tenacity zone discovery reported in late 20256
.
Utilising updated geological domains and the additional drilling data obtained through to March 2026,
the Resolution Lode Resource was upgraded to 4,110kt grading at 2.71g/t Au for 358koz of Inferred
Resources, delivering a considerable increase of tonnes (+28%), grade (+6%) and an additional 94koz of
Inferred gold ounces (+36%).
The Resolution Lode comprises open pit (4% increase compared to 2021 MRE) and underground
mineralisation (61% increase), with the substantial increase demonstrating the importance of developing
and evolving the understanding and application of robust geological interpretation and domaining,
combined with the exploration strategy of drilling targeting mineral extensions within identified
Exploration Target areas.
Table 1 – Aureka’s Updated Global Mineral Resources June 2026
4
ASX Release 18 June 2026: Global JORC Resource Increase to over 450koz
5
ASX Release 18 June 2026: Global JORC Resource Increase to over 450koz
6
ASX Release 15Oct 2025: Irvine Drilling Highest Assay Since Discovery
7
ASX Announcement: 13 Jun 2025: AKA - St Arnaud Maiden JORC MRE and Exploration Target Amended.
Prospect
Cut-Off
Gold (g/t)
Inferred
Tonnes Gold Grade (g/t) Gold Ounces
Resolution Open Pit* >0.5 1,775,000 2.16 123,000
Adventure Open Pit >0.6 680,000 1.85 40,300
Total Irvine (Stawell)
Open Pit*
Various 2,455,000 2.07 163,300
Resolution
Underground*
>1.0 2,335,000 3.13 235,000
Total Irvine (Stawell) Various 4,790,000 2.59 398,300
Comstock (St Arnaud)7
>0.5 1,450,000 1.21 56,500
Total All Projects Various 6,240,000 2.27 454,800
ASX : AKA B R I N G I N G V I C T O R I A ' S G O L D T O L I F E 3
30 JULY 2026
Figure 1 - Irvine Gold Project in the Stawell Corridor – The project consists of 2 gold lodes - Resolution Lode (LHS) (revised JORC
Resource in this announcement) and the Adventure Lode (RHS, JORC Resource published in March 2021).
Table 2 - Irvine Gold Project - Resolution Lode only - Mineral Resources June 2026
Updated JORC estimates for the Resolution Lode of the Irvine Gold Project, the subject of this announcement.
The preceding Statement of Mineral Resources conforms to the Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves (JORC Code) 2012 Edition. All tonnages reported are dry metric tonnes. Minor discrepancies may occur
due to rounding to appropriate significant figures.
Prospect
Cut-Off
Gold (g/t)
Inferred
Tonnes Gold Grade (g/t) Gold Ounces
Resolution Open Pit >0.5 1,775,000 2.16 123,000
Resolution UG >1.0 2,335,000 3.13 235,000
Total Resolution Various 4,110,000 2.71 358,000
ASX : AKA B R I N G I N G V I C T O R I A ' S G O L D T O L I F E 4
30 JULY 2026
Figure 2 - Resolution Lode at the Irvine Gold Project in the Stawell Corridor which has been the subject of Aureka’s diamond
drilling thus far and Estimated JORC Resource updated with this release.
The JORC Resource at the nearby Adventure Lode (2km to SE), was released in March 2021.
Figure 3 – Long section looking west of the Resolution Lode showing Resolution Fault and Tenacity Fault
ASX : AKA B R I N G I N G V I C T O R I A ' S G O L D T O L I F E 5
30 JULY 2026
Exploration Targets also updated during June Quarter
In addition to the JORC compliant Global Mineral Resource update, a review of the Irvine Exploration
Target was completed during the quarter defining both Advanced Targets (based on possible along strike
continuity) ranging from 0.88kt to 1.76kt and grades 2g/t-2.3g/t gold and Conceptual Exploration Targets
(based on targets that exist to the west of the main lode at the Irvine Project) 2.35kt to 4.7kt with grade
range 2-2.3g/t gold.
Table 3 – Irvine Gold Project Resolution lode – Updated Exploration Target Range
Prospect: Irvine Gold
Project
Exploration Target Range*
Tonnes (Mt) Gold Grade (g/t) Gold Ounces (k Oz)
Advanced Targets* 1.33 – 2.66 2.0 – 2.3 85 - 197
Conceptual Targets* 2.35 – 4.7 2.0 - 2.3 151 - 348
*The potential quantity and grade of the Exploration Target is conceptual in nature and there has been insufficient exploration to
estimate a Mineral Resource in relation to this Exploration Target. It is uncertain if further exploration will result in the estimation
of a Mineral Resource in relation to these Exploration Targets
Advanced Exploration Target (ET)
ET 1 (Figure 5 and Figure 4) is categorised as Advanced since it is up-dip of known Mineral Resources.
This area remains untested with respect to drilling; however, forms part of the current exploration
strategy.
Figure 4 - Long section looking northeast showing ET 1 and the Resolution Zone (note – widths are downhole intercepts)
Shallow air core drill holes drilled 20168
near the contact with the Resolution Zone did not intersect ore
grade mineralisation. However taking into consideration the strike extents to the south, there are no
reasons to suggest that the entire area is devoid of mineralisation. Therefore, this area is considered
highly prospective, with likely extensions of mineralisation up-dip of the current Mineral Resource.
8
ASX Release 16 Jan 2017: Discovery of multiple surfaces of gold mineralisation at Irvine prospect near Stawell, Victoria
ASX : AKA B R I N G I N G V I C T O R I A ' S G O L D T O L I F E 6
30 JULY 2026
Utilising upper limit parameters of a strike length of 540m, a down dip of 400m (excludes the area of
shallow AC holes and only includes fresh rock material), a width of 3m, a density of 3.8 g/cc and a times
two reduction (excludes strike / dip that has been reported as Resolution Zone within the MRE) resulted
in approximately 900kt. Since the exact dimensions are unknown, a lower limit of half the upper limit
results in 450kt, and because ET 1 is an up-dip extension of known mineralisation, the expected grade
range for ET1 is between 2.0 g/t gold and 2.3 g/t gold which is based on the average grade of the
Resolution Zone (2.16 g/t gold).
ET 2 is also categorised as Advanced since it too is along strike of known Mineral Resources. There are
also some air core holes with geochemistry anomalies including 9m @ 2.1 g/t gold from hole IAC4529
.In
addition, the magnetics shown in Figure 5 show an area of demagnetisation similar to the Resolution
zone as well as an IP anomaly (not shown).
The current interpreted trend of the mineralisation suggests that it daylights to the north however, given
the information previously mentioned, it is possible that the interpreted plunge is incorrect (i.e. the
plunge may be to the south or there may be faulted offsets) and mineralisation may be present to the
north.
Utilising upper limit parameters of a 1,500m strike length, a down dip of 100m, a width of 5m and a
density of 2.35 g/cc results in a total of 1,760,000 tonnes and since the exact dimensions are unknown, a
lower limit of half the upper limit results in 880,000 tonnes.
The grade intercept from hole IAC452 (2.1 g/t gold) and from the Resolution MRE upper zone (2.16 g/t
gold) suggest that gold grades near surface are proximal to these values. Therefore, the expected grade
range for ET 2 is between 2.0 g/t gold and 2.3 g/t gold.
Conceptual Exploration Targets
An additional 4 Exploration targets exist to the west of the main line of lode. These form extensions to
known historic mines. Broad trends are evident on the TMI image (Figure 5) however there is a lack of
modern sampling data.
The upper limit to define the volume / tonnage is as follows; Strike – 4,000m, Down-dip – 100m.
Width – 5m, Density – 2.35 g/cc which resulted in a total of 4,700,000 tonnes. Again, because the exact
dimensions are unknown, a lower limit of half the upper limit resulted in 2,350,000 tonnes with expected
ranges assumed to be similar to ET 1 i.e. 2.0 g/t gold and 2.3 g/t gold.
5
ASX Release 18 June 2026: Global JORC Resource Increase to over 450koz
ASX : AKA B R I N G I N G V I C T O R I A ' S G O L D T O L I F E 7
30 JULY 2026
Figure 5 - Plan view of Exploration Targets overlain on RTP TMI Tilt image. ET1 & ET2 have been classified as Advanced Exploration
Targets, while ET3-6 are Conceptual Exploration Targets.
ASX : AKA B R I N G I N G V I C T O R I A ' S G O L D T O L I F E 8
30 JULY 2026
EXPLORATION ACTIVITIES
Irvine Gold Project (Stawell Zone) –drilling and improved geophysical understanding
Drilling activities remained ongoing at Irvine throughout the quarter with a focus on step out drilling
several key areas regional to the main Irvine Lodes with potential to deliver step change discoveries,
supported by elevated legacy geochemistry and favourable geophysical responses. Assay results remain
pending and are expected to be finished during the September quarter.
Interpretation of the magnetics dataset acquired during the March quarter remained ongoing during the
June quarter. The increased magnetic data resolution clearly defines subsurface geological features and
enhances targeting opportunities within the Irvine Gold Project. Interpretation of the dataset has better
defined the underlying structural architecture and has in turn identified several new key areas of interest,
areas that feature emerging structural complexity which were incorporated into the Explration Target
review and provide increased support for additional discoveries within the greater Irvine mineral system;
including the under-explored “gap” between Resolution and Adventure Lodes where two targets have
been identified (Figure 5).
Further detailed geological interpretation and assessment for additional targeting opportunities remains
in progress. Distinguished geologist, Dr Barry Murphy, whose regional geological interpretations and
targeting directly led to the discovery of Predictive Discovery’s 5.5Moz Bankan Gold Project in Guinea,
West Africa9
, has been engaged to assist with the assessment and targeting.
Figure 6 A&B. Side by side comparison between the reprocessed legacy TMI shape index magnetics data (Fig A) with the newly
acquired drone magnetics data (Fig B). The tighter 50m-spaced drone magnetics provides enhanced local-scale resolution
enabling identification of contrasting magnetic responses and possible emerging second order structures that provide further
local scale targeting opportunities with potential to deliver new mineral discoveries at Irvine
9
ASX Release 5 June 2026: MAG Survey Identifies New High Priority Targets
Fig 6A Fig 6B
ASX : AKA B R I N G I N G V I C T O R I A ' S G O L D T O L I F E 9
30 JULY 2026
Figure 7 A&B. Side by side comparison between the reprocessed legacy TMI RTP magnetics analytic signal filter (Fig A) with the
newly acquired drone magnetics data (Fig B). Fig 4B demonstrated the improved increase in contrasting magnetic responses and
subtle variation not identified with the coarser legacy data and also notes the possible emerging second order structures that
provide further local scale targeting opportunities with potential to deliver new mineral discoveries at Irvine.
St Arnaud – Comstock Project – Commencement of infill and reaffirmation drilling
Diamond drilling at the Comstock project recommenced during the quarter aiming to validate data from
historical drilling results, and also increase drill data density to, if successful, support a higher confidence
level for sections of the 100% Inferred 56koz JORC Resource10
.
The drilling completed during the quarter has been primarily focused within the Walker pit at the
Comstock Gold Project. The objective of this drilling is to target continuity beneath Walkers pit and
confirm historical drill hole data. Successful drilling and assays would, assuming acceptable assay results,
upgrade the JORC Resource to higher classification to underpin production target statement and financial
forecasts for the first production stage at Comstock. Assay results for the drilling completed to date
remain pending and are expected to be finalised and reported during the September quarter.
s
ASX Release 13 June 2025: St Arnaud Maiden JORC MRE and Exploration Target - Amended
Fig 7A Fig 7B
ASX : AKA B R I N G I N G V I C T O R I A ' S G O L D T O L I F E 10
30 JULY 2026
Figure 8 – View of the high-accuracy LiDAR and photogrammetry of the Comstock open-cut pit – looking towards the South
(azimuth 18). Red circle highlights drill target area for the 6-week infill diamond drilling program now underway.
ASX : AKA B R I N G I N G V I C T O R I A ' S G O L D T O L I F E 11
30 JULY 2026
Figure 9– Plan View of the Walkers sub-pit and the Walkes main Shear with legacy drill intercepts projected to pit floor surface9
.
9
ASX Release 29 May 2026: Infill Drilling Commences at Comstock
ASX : AKA B R I N G I N G V I C T O R I A ' S G O L D T O L I F E 12
30 JULY 2026
Table 4: Comstock Project estimated Mineral Resources in accordance with the 2012 edition of JORC Code10
The preceding statements of Mineral Resources conform to the Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves (JORC Code) 2012 Edition. All tonnages reported are dry metric tonnes. Minor discrepancies may occur
due to rounding to appropriate significant figures.
Table 5: Comstock Project estimated Exploration Target in accordance with the 2012 edition of JORC Code11
Exploration Strategy Overview
Diamond drilling at both the flagship Irvine Project and the Comstock Project remains the focus over the
coming quarter. Drilling activities at Irvine will drill test dip and strike continuity of key areas of interest
proximal to the Resolution lode where data density is comparatively low.
The drilling aims to demonstrate continuity to mineralisation beyond the recently update MRE and
maintain the growth strategy of developing Irvine beyond 1Moz; while at Comstock, the drilling will
continue to confirm and infill legacy drill hole data and aims to ultimately deliver an upgrade of the JORC
Resource that will be used to support a production target statement and financial forecasts for the first
production stage at Comstock.
10
ASX Release 13 June 2025: St Arnaud Maiden JORC MRE and Exploration Target - Amended
11
ASX Release 13 June 2025: St Arnaud Maiden JORC MRE and Exploration Target - Amended
Prospect
Cut-Off
Gold
(g/t)
Inferred
Tonnes Gold Grade
(g/t)
Gold
Ounces
Grade
(g/t)
silver
Silver
(oz)
Comstock (St
Arnaud)
>0.5 1,450,000 1.21 56,500 2.14 100,00
Prospect
Exploration Target*
Range Tonnes
(Mt)
Gold
Grade
(g/t)
Gold
ounces (k
Oz)
Silver
Grade
(g/t)
Silver
ounces (k
Oz)
Comstock (St
Arnaud)
Lower 3.0 1.2 116 2.02 195
Upper 3.5 1.0 112 1.90 214
*The potential quantity and grade of the Exploration Target is conceptual in nature and there has been insufficient exploration
to estimate a Mineral Resource in relation to this Exploration Target. It is uncertain if further exploration will result in the
estimation of a Mineral Resource in relation to these Exploration Targets.
ASX : AKA B R I N G I N G V I C T O R I A ' S G O L D T O L I F E 13
30 JULY 2026
Tenement Update
During the quarter the following updates to the Company’s tenement status occurred:
• Prospecting licence application: Application PL008915 was submitted covering the Walkers Pit area
of the Comstock Gold & Silver Project. No competing applications were received and the company
recently received approval to commence applicable advertising.
• Pending applications for EL008923 and EL008976: Applications submitted to secure prospective
ground west and contiguous to the Company’s Stawell Corridor project.
• Exploration Licences EL007751 and EL007752 were surrendered: both distal to the main Jubilee
Project near Ballarat, provided no value to the portfolio due to assessed low overall prospectivity.
Refer to the table below for full updated tenement listing.
FINANCIAL
Expenditure During the Period
The Company’s major cashflow movements for the quarter included:
• Exploration and evaluation costs – ($849k),
• Employee, administration and corporate costs – ($525k),
• Cash and cash equivalents (unaudited) of $2.3m as at end June 2026.
Payments to Related Parties and their Associates
In the June 2026 quarter, $129k was paid to related parties and their associates in respect of salaries and
fees (including superannuation) paid to non-executive directors and the managing director.
CORPORATE ACTIVITIES
On 5 June 2026, Amy Monteith, of CSB Corporate Services was appointed as Company Secretary, providing
support to the Company’s Directors and Executives.
FUTURE OUTLOOK AND SUMMARY
Focus in the coming quarter will be to remain with two drill rigs continually drilling at both the flagship Irvine
Project exploring potential extension to the 398koz12
inferred JORC resources already defined and the St
Arnaud Comstock Project (56koz inferred JORC13
) as the company continues to advance the project towards
delivering a near-term small-scale production opportunity.
This announcement has been approved for release by the Board.
For further information, please contact:
James Gurry
Managing Director
James.Gurry@aureka.com.au
+61 451 349 688
12
ASX Release 18 June 2026: Global JORC Resource Increase to over 450koz
13
ASX Release 13 June 2025: St Arnaud Maiden JORC MRE and Exploration Target - Amended
ASX : AKA B R I N G I N G V I C T O R I A ' S G O L D T O L I F E 14
30 JULY 2026
TENEMENT STATUS
The mineral tenement holding of the Aureka as of 30 June 2026 (Bold text indicates status change):
Name Tenement Tenure Type Status Interest
STAWELL CORRIDOR GOLD PROJECT (south of Stawell, Victoria)
Ararat EL 5476 Exploration Licence Granted 100%
Tatyoon EL 5480 Exploration Licence Granted 100%
Glenlyle EL 5497 Exploration Licence Granted 100%
Long Gully EL 006525 Exploration Licence Granted 100%
Westgate EL 006526 Exploration Licence Granted 100%
Petticoat Gully / HH EL 006527 Exploration Licence Granted 100%
Dutton / Napolean EL 006528 Exploration Licence Granted 100%
Eastern Maar ELA 006530 Exploration Licence Application 0%
Langi Logan EL 006702 Exploration Licence Granted 100%
Langi Logan West EL 006745 Exploration Licence Granted 100%
Margaret Gully ELA 006843 Exploration Licence Application 0%
Mininera EL 007125 Exploration Licence Granted 100%
Tatyoon North EL 007743 Exploration Licence Granted 100%
Goldburra ELA 008923 Exploration Licence New Application 0%
Pinkey ELA 008976 Exploration Licence New Application 0%
ST ARNAUD GOLD PROJECT (north of Stawell, Victoria)
Comstock (Walkers) PL008915 Prospecting Licence New Application 100%
St Arnaud EL 006556 Exploration Licence Granted 100%
Lord Nelson EL 006819 Exploration Licence
Granted/Renewed until
203014
100%
St Arnaud West EL 007436 Exploration Licence Granted 100%
Donald EL 007496 Exploration Licence Granted 100%
Jeffcott EL 007567 Exploration Licence Granted 100%
Donald EL 008117 Exploration Licence Granted 100%
STAVELY ARC PROJECT (west of Stawell, Victoria)
Stavely EL 5425 Exploration Licence Granted 15.63%3
JUBILEE GOLD PROJECT (west of Ballarat, Victoria)
Jubilee EL 006689 Exploration Licence Granted 100%
East Jubilee EL 007748 Exploration Licence Granted 100%
Snake Valley EL 007751 Exploration Licence Relinquished 0%
Nintingbool EL 007752 Exploration Licence Relinquished 0%
1
EL 5476 contains the Irvine Project JORC Resource
3
To be Transferred to Stavely Minerals Limited
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
General
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Aureka Limited
ABN Quarter ended (“current quarter”)
66 125 140 105 30 June 2026
Consolidated statement of cash flows Current quarter
$A’000
Year to date (12
months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
(849) (3,486)
(a) exploration & evaluation
(b) development - -
(c) production - -
(d) staff costs (214) (728)
(e) administration and corporate costs (311) (1,760)
1.3 Dividends received (see note 3) - -
1.4 Interest received 8 8
1.5 Interest and other costs of finance paid - -
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other (provide details if material) - -
1.9 Net cash from / (used in) operating
activities
(1,366) (5,966)
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
(a) entities
(b) tenements - -
(c) property, plant and equipment - (833)
(d) exploration & evaluation - -
(e) investments - -
(f) other non-current assets - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
General
Consolidated statement of cash flows Current quarter
$A’000
Year to date (12
months)
$A’000
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments (Tandarra divestment) - 1,275
(e) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (deposit for property acquisition) - (368)
2.6 Net cash from / (used in) investing
activities
- 74
3. Cash flows from financing activities
- 3,590
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options - -
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
(4) (285)
3.5 Proceeds from borrowings - -
3.6 Repayment of borrowings - -
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other (repayment of lease liabilities) - (48)
3.10 Net cash from / (used in) financing
activities
(4) 3,257
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
3,671 4,936
4.2 Net cash from / (used in) operating
activities (item 1.9 above)
(1,366) (5,966)
4.3 Net cash from / (used in) investing activities
(item 2.6 above)
- 74
4.4 Net cash from / (used in) financing activities
(item 3.10 above)
(4) 3,257
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 3
+ See chapter 19 of the ASX Listing Rules for defined terms.
General
Consolidated statement of cash flows Current quarter
$A’000
Year to date (12
months)
$A’000
4.5 Effect of movement in exchange rates on
cash held
- -
4.6 Cash and cash equivalents at end of
period
2,301 2,301
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances 2,301 3,671
5.2 Call deposits - -
5.3 Bank overdrafts - -
5.4 Other (provide details) - -
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
2,301 3,671
6. Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1 Aggregate amount of payments to related parties and their
associates included in item 1
129
6.2 Aggregate amount of payments to related parties and their
associates included in item 2
-
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 4
+ See chapter 19 of the ASX Listing Rules for defined terms.
General
7. Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1 Loan facilities - -
7.2 Credit standby arrangements - -
7.3 Other (please specify) - -
7.4 Total financing facilities - -
7.5 Unused financing facilities available at quarter end -
7.6 Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
N/A
8. Estimated cash available for future operating activities $A’000
8.1 Net cash from / (used in) operating activities (item 1.9) (1,366)
8.2 (Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
-
8.3 Total relevant outgoings (item 8.1 + item 8.2) (1,366)
8.4 Cash and cash equivalents at quarter end (item 4.6) 2,301
8.5 Unused finance facilities available at quarter end (item 7.5) -
8.6 Total available funding (item 8.4 + item 8.5) 2,301
8.7 Estimated quarters of funding available (item 8.6 divided by
item 8.3)
1.68
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8 If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1 Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: No. The company expects operating cash out flow to slow as the infill diamond
drilling campaign at Comstock concludes in coming weeks.
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 5
+ See chapter 19 of the ASX Listing Rules for defined terms.
General
8.8.2 Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: Steps include pursing the production strategy as evidenced by the recent toll
milling agreement and production licence application, potential monetisation of non-
Share your feedback