P a g e |1
30 July 2015
June 2015 Quarter
Report to Shareholders
ASX Code: NML
KEY POINTS:
Ararat Exploration Licence (EL 5476)
Two new outcropping gold prospects, Irvine and Benno, discovered
from surface mapping and gossan sampling near Stawell, western
Victoria.
Numerous surface gold results up to 8.3 grams per tonne in rock-chip
sampling recorded along the 1.6km strike of the Irvine basalt dome.
Navarre Minerals Limited
ABN 66 125 140 105
Corporate Details
Issued capital:
92.6M ordinary shares
2.3M unlisted options
Tatyoon Exploration Licence (EL 5480)
1,500m drilling program at the Grange gold prospect confirmed
presence of extensive sulphide alteration as predicted in IP
geophysics but assay results downgraded the prospectivity of the
western flank target.
Directors & Management:
Kevin Wilson
(Non-Executive Chairman)
Geoff McDermott
(Managing Director)
Tandarra Exploration Licence (EL 4897)
High-grade gold intersected in reconnaissance drilling by project
manager Catalyst Metals Limited
John Dorward
(Non-Executive Director)
Corporate
$150,000 raised from placement of Entitlement Offer shortfall.
Program of cost control measures, including salary reductions for
senior management, implemented to ensure maximum funding for
exploration of premier assets.
Colin Naylor
(Non-Executive Director)
Jane Nosworthy
(Company Secretary)
Wessley Edgar
(Exploration Manager)
MANAGING DIRECTOR’S REVIEW
The highlight of the quarter was the discovery of two new outcropping gold
prospects, Irvine and Benno, on the Company’s recently granted Ararat
Exploration Licence (EL 5476), part of the 100%-owned Stawell Corridor Gold
Project (Figure’s 1 and 2). Over half of the rock chip samples assayed reported
anomalous gold, with 20% containing more than 1g/t gold. Together with the
extensive local historic alluvial workings, this represents a significant untested
geochemical gold anomaly which strongly suggests Stawell-style gold
mineralisation.
Contact Details
Geoff McDermott
Managing Director
Navarre Minerals Limited
40 – 44 Wimmera Street
Stawell VIC 3380
Australia
The Irvine and Benno prospects occupy the northern end of the historic Ararat
Goldfield which is estimated to have produced approximately one million ounces
of gold mainly from alluvial and deep lead production during the period 1854 to
1925.
PO Box 385
Stawell VIC 3380
Australia
Tel: +61 (0)3 5358 8625
Email: info@navarre.com.au
Website: www.navarre.com.au
Historically, production of primary hard-rock gold from the Ararat Goldfield was
low given the richness of the alluvial deposits, and it therefore offers the Company
a compelling reason to search for economic mineralisation in the vicinity of the
richest alluvial gold deposits.
Navarre Minerals Limited | ABN 66 125 140 105
40 - 44 Wimmera Street | PO Box 385 | Stawell VIC 3380 Australia
t +61 3 5358 8625
e info@navarre.com.au | w navarre.com.au
Navarre Minerals Limited ASX Announcement
P a g e |2
Navarre also announced the results of the recently completed first pass drilling program at the Grange gold
prospect on the Company’s Tatyoon exploration licence (EL 5480), also part of the Stawell Corridor Gold Project.
Figure 1: Location of Navarre’s Victorian mineral projects.
1.
EXPLORATION
STAWELL CORRIDOR GOLD PROJECT (EL 5480 & EL 5476)
Navarre’s Stawell Corridor Gold Project, incorporating the Ararat and Tatyoon exploration licences and the historic
Ararat Goldfield, is located between 10 and 70 kilometres south-east of the operating Stawell Gold Mine which is
owned by Navarre’s largest shareholder and leading Victorian gold producer, Newmarket Gold Inc. (formerly
Crocodile Gold Corp.).
Ninety percent of the prospective Stawell Corridor lies buried beneath shallow cover, only to surface between
Stawell and Ararat where approximately 6 million ounces of historic and modern gold production has occurred
(Figure’s 1 & 2).
Navarre Minerals Limited | ABN 66 125 140 105
40 - 44 Wimmera Street | PO Box 385 | Stawell VIC 3380 Australia
t +61 3 5358 8625
e info@navarre.com.au | w navarre.com.au
Navarre Minerals Limited ASX Announcement
P a g e |3
Modern gold mining at Stawell has been continuous since 1982 and has contributed more than 2 million ounces
of the total 5 million ounce historic gold production for the Stawell Goldfield. Gold mineralisation of the Stawellstyle is located on the flanks of large basalt dome structures. The style of the gold mineralisation is much finer
grained, more continuous and more predictable than the gold deposits typically found at Victoria’s largest two
goldfields at Bendigo and Ballarat.
Figure 2: Plan of the Stawell Corridor Gold Project tenements and Stawell-style targets.
Ararat (EL 5476)
New gold prospects on Ararat licence – Irvine and Benno
Reconnaissance mapping and sampling has led to the discovery of outcropping Stawell-style basalt-contact
mineralisation at the Irvine gold prospect, where gold mineralisation grading up to 8.3 g/t gold is reported from
rock chip samples taken along a 1.6km strike of the basalt dome (Figure 3). Over half of the 71 rock chip samples
collected during the quarter assayed over 0.1 g/t of gold and more than 20% reported higher than 1 g/t of gold
(Figure 4 & Table 1; see NML’s ASX release of 12 June 2015).
Geological appraisal of the larger (2.3km strike) Benno prospect is less advanced but initial sampling has produced
encouraging gold results of over 1 g/t gold above a strong magnetic anomaly.
Figure 4 presents an image of airborne magnetics overlain by the locations of all rock chip samples from Irvine
and Benno, together with an interpretive outline of the geology derived from geophysics, surface mapping and
previous drill results.
Navarre Minerals Limited | ABN 66 125 140 105
40 - 44 Wimmera Street | PO Box 385 | Stawell VIC 3380 Australia
t +61 3 5358 8625
e info@navarre.com.au | w navarre.com.au
Navarre Minerals Limited ASX Announcement
P a g e |4
Figure 3: Aeromagnetic image and geological fault interpretation surrounding the Stawell
Granite showing the symmetry of structure and location for the Stawell Gold
Mine and Navarre’s new prospects, Benno and Irvine, in the northern Ararat
Goldfield. The named Stawell Fault south of Irvine is the interpreted equivalent
fault to that near Magdala based on structural re-construction of the northern
Ararat region.
Anomalous gold rock chip samples, summarized in Table 1 and shown in Figure 4, are defining several high-priority
‘Stawell-style’ gold mineralised surfaces. Significant gold mineralisation includes:
1.
a basalt contact surface located on the western side of the Irvine Basalt with gold results up to 8.30 g/t;
2.
a basalt contact surface on the eastern side of the Irvine Basalt with gold results up to 4.90 g/t;
3.
two hangingwall surfaces (Native Youth line) comprising lines of ironstone and gossan west of the Irvine
Basalt with gold results up to 3.34 g/t; and
4.
a single outcrop of mineralised sediment at the Benno prospect with a gold result of 1.03 g/t.
Navarre Minerals Limited | ABN 66 125 140 105
40 - 44 Wimmera Street | PO Box 385 | Stawell VIC 3380 Australia
t +61 3 5358 8625
e info@navarre.com.au | w navarre.com.au
Navarre Minerals Limited ASX Announcement
P a g e |5
Follow-up exploration is likely to include:
1.
further geological mapping and rock chip sampling, particularly at Benno;
2.
soil geochemical sampling; and
3.
planning for detailed geophysical surveys to identify and refine targets for drilling.
Figure 4: Gold in Rock Chip assay results from surface sampling and mapping at the Irvine
and Benno prospects. Historical drill results and drill traces are also shown. The
underlying image is an airborne magnetic (TMI) image. Gold grades are
rounded to 0.1g/t gold.
Navarre Minerals Limited | ABN 66 125 140 105
40 - 44 Wimmera Street | PO Box 385 | Stawell VIC 3380 Australia
t +61 3 5358 8625
e info@navarre.com.au | w navarre.com.au
Navarre Minerals Limited ASX Announcement
P a g e |6
Tatyoon (EL 5480)
Initial drill program completed at Grange gold prospect
On 12 June 2015, the Company announced the results of its first pass drill program into the Grange basalt dome
target (Figure 2).
The drill program, comprising 6 RC and 3 diamond drill holes for a total of 1,500 metres, tested the main
chargeability targets defined from induced polarisation (“IP”) geophysical surveys. These targets were detected
in basement rocks hidden beneath cover rocks comprising recent volcanics, quartz gravels and sands.
The drilling intersected broad zones of disseminated sulphide (pyrite and/or pyrrhotite) alteration and associated
quartz veining within meta-sediments adjacent to the Grange basalt dome. This is interpreted to be of sufficient
intensity and distribution to explain the IP chargeability response.
The sulphide alteration located on the west flank of the dome appears to lack the intensity required to form
economic mineralisation, where tested. The west flank basalt contact was also revealed to be complexly mixed
with surrounding meta-sediments. In line with these observations, assay results returned from all holes which
achieved target depths report minor gold mineralisation. The best result was 1m @ 1.18 g/t gold from 94m downhole in RCT005 (see NML ASX release 12 June 2015). The results have down-graded the prospectivity of the
western side of the Grange basalt dome.
Following completion of first pass drilling at Grange, the Company is appraising the Hermitage and Shiraz basalt
domes as well as the east flank of the Grange dome. In conjunction with Monash University researchers,
additional gravity surveying has been acquired and is being processed to refine the geometry and position of these
basalt dome structures beneath the cover sequences.
TANDARRA GOLD PROJECT (EL 4897)
The Tandarra Gold Project is a greenfields gold discovery under shallow cover, 40km north of the 22 million ounce
Bendigo Goldfield (Figure 1). Project manager Catalyst Metals Limited (“Catalyst”) has the right to earn a 51%
equity interest in the Tandarra Gold Project by incurring exploration expenditure of $3 million over four years to
September 2018.
On 29 July 2015 Catalyst reported that it had completed its first reconnaissance air-core drilling program at
Tandarra under its stewardship, which comprised 3,853 metres of reconnaissance air-core drilling in 31 holes on
3 drill traverses (refer Catalyst ASX release 29 July 2015).
The highlight of the drilling was an intersection of high-grade gold and another significant zone of mineralisation,
approximately 500 metres apart:
2.0m @ 33.1 g/t Au including 1.0 m @ 65.6g/t Au from 129 metres (ACT221)
5.0m @ 0.5 g/t Au from 78 metres (ACT202)
These intersections are located about seven kilometres north on strike of the main zone of high grade gold
mineralisation at the Tomorrow Prospect and approximately seven kilometres south of Catalyst’s Four Eagles Gold
Project (Figure 5). This new zone of mineralisation is virtually untested over a 14 kilometre strike and will require
considerably more air-core drilling to evaluate the potential.
Catalyst also reported it had commenced an evaluation of drill results at the Tomorrow Prospect in preparation
for completing a mineralisation report by December 2015.
Navarre Minerals Limited | ABN 66 125 140 105
40 - 44 Wimmera Street | PO Box 385 | Stawell VIC 3380 Australia
t +61 3 5358 8625
e info@navarre.com.au | w navarre.com.au
Navarre Minerals Limited ASX Announcement
P a g e |7
ACT221: 2m @ 33.0g/t Au
ACT202: 5m @ 0.5g/t Au
Tomorrow Prospect
Figure 5:
Tandarra Gold Project showing interpreted gold zones and air core drilling (map
reproduced courtesy of Catalyst Metals Limited; see Catalyst Metals ASX release 29 July 2015) .
Navarre Minerals Limited | ABN 66 125 140 105
40 - 44 Wimmera Street | PO Box 385 | Stawell VIC 3380 Australia
t +61 3 5358 8625
e info@navarre.com.au | w navarre.com.au
Navarre Minerals Limited ASX Announcement
P a g e |8
WESTERN VICTORIA COPPER PROJECT (ELs 4590, 5425, 5426 & 5497)
Navarre’s 100%-owned Western Victoria Copper Project captures multiple, largely untested targets in 130km of
Miga Arc volcanics (Figure 1), including the Eclipse, Lexington, Glenlyle and Pollockdale prospects. The Miga Arc
is recognised as a continental margin arc setting similar to the Andes, host to the world’s largest known copper
porphyry deposits.
Most areas across the Miga Arc are presently being geologically re-interpreted at a regional scale by the Geological
Survey of Victoria, including the Black Range exploration licence area using Navarre’s high resolution
aeromagnetics, and the Eclipse Prospect where new gravity data was obtained in the quarter by Monash
University researchers.
LANDSBOROUGH FAULT GOLD PROJECT (EL 5280)
No exploration activity was undertaken during the quarter.
2.
ACTIVITIES PLANNED FOR THE SEPTEMBER QUARTER
Stawell Corridor Gold Project:
Further geological mapping and rock chip sampling, at Irvine and Benno;
Soil geochemical sampling; and
Commencement of detailed geophysical surveys to identify and refine targets for drilling.
Tandarra Gold Project (managed by Catalyst Metals Limited):
Preparation of Tomorrow Prospect mineralisation report
Plan infill and step-out drill program as follow-up to high-grade gold
3.
CORPORATE
Capital raising
As announced on 24 April 2015, the Company completed a placement of 5,000,000 shortfall shares (Shortfall
Shares) from its 1 for 4 non-renounceable pro rata entitlement offer (Entitlement Offer), which closed on 13
March 2015, to raise an additional $150,000.
The Shortfall Shares were issued at the Entitlement Offer price of $0.03 per share to professional and
sophisticated investors, including major shareholder Newmarket Gold Inc., which subscribed for 2,000,000
Shortfall Shares.
Review of Research & Development Tax Incentive Registration
The Company’s R&D tax incentive registration for the 2011/12 year remains under review by AusIndustry,
following notification in December 2014 that the registration was considered to have a high risk of noncompliance with the eligibility requirements of the R&D Tax Incentive program. During the quarter, the Company
submitted further additional evidence in support of its claimed R&D activities.
The Company and its external R&D tax consultants continue to believe that the Company’s R&D registration is in
compliance with the requirements of the R&D Tax Incentive program. However, there is a risk that AusIndustry
may disagree with the Company’s assessment of the eligibility of its claimed R&D activities under the program
and make a finding that some or all activities are ineligible under the program.
Navarre is awaiting AusIndustry’s response to the Company’s submissions.
Navarre Minerals Limited | ABN 66 125 140 105
40 - 44 Wimmera Street | PO Box 385 | Stawell VIC 3380 Australia
t +61 3 5358 8625
e info@navarre.com.au | w navarre.com.au
Navarre Minerals Limited ASX Announcement
P a g e |9
Cash position
The cash balance as at 30 June 2015 was $0.5 million ($0.9 million at 31 March 2015).
Cost Management and Control
As a result of external economic conditions and the prevailing market sentiment towards resource companies,
Navarre is implementing a range of cost reduction measures to ensure it manages its cash position while retaining
the ability to undertake further exploration, in particular on the two new gold prospects, Irvine and Benno,
recently identified as part of the Company’s Stawell Corridor Gold Project.
All staff have agreed to reductions in salary or hours of work, including a 40% salary reduction for the Managing
Director, and the Company’s non-executive directors have agreed to defer payment of directors’ fees. It is
expected that these measures will be in place until such time as the Company’s cash position improves
significantly as the result of improved economic conditions, exploration success and/or better access to equity
markets.
In accordance with the Company’s remuneration philosophy, the Company is considering issuing equity
incentives, such as shares or share options, in lieu of salary forgone by senior management or directors.
Shareholder approval will be required for any equity incentives to be granted to directors.
The Company is also implementing a number of additional cost cutting measures, including reductions in staffing
levels and overheads.
Together, these measures are expected to deliver a significant reduction in corporate overheads.
Commenting on the changes, Navarre Managing Director, Geoff McDermott, said, “The Company continues to be
mindful of the external economic conditions currently affecting the resource industry and has responded with a
considered and methodical program of cost control while continuing to explore its premier exploration assets.”
4.
MINERAL TENEMENT PORTFOLIO
The mineral tenement holding of the Navarre Minerals Limited Group (including Navarre’s wholly-owned
subsidiary Black Range Metals Pty Ltd) at 30 June 2015 is:
Name
Tenement
Tenure Type
TANDARRA GOLD PROJECTS (north of Bendigo, Victoria)
Tandarra
EL 4897
Exploration Licence
LANDSBOROUGH FAULT GOLD PROJECT (east of Stawell, Victoria)
Kingston
EL 5280
Exploration Licence
STAWELL CORRIDOR GOLD PROJECT (south of Stawell, Victoria)
Ararat
EL 5476
Exploration Licence
Tatyoon
EL 5480
Exploration Licence
WESTERN VICTORIA COPPER PROJECT (west of Stawell, Victoria)
Black Range
EL 4590
Exploration Licence
Stavely
EL 5425
Exploration Licence
Cherrypool
EL 5426
Exploration Licence
Glenlyle
EL 5497
Exploration Licence
Status
NML Group Interest
Granted
100%*
Granted
100%
Granted
Granted
100%
100%
Granted
Granted
Granted
Granted
100%
100%
100%
100%
*The Company has granted Catalyst Metals Limited the right to earn a 51% interest in Tandarra by expenditure of $3 million over a four
year period to September 2018.
Navarre Minerals Limited | ABN 66 125 140 105
40 - 44 Wimmera Street | PO Box 385 | Stawell VIC 3380 Australia
t +61 3 5358 8625
e info@navarre.com.au | w navarre.com.au
Navarre Minerals Limited ASX Announcement
P a g e | 10
The Company’s beneficial interests in any farm-in or farm-out agreements did not change during the quarter,
except as specifically stated elsewhere in this Report.
– ENDS –
About Navarre Minerals Limited:
Navarre Minerals Limited (ASX: NML) is an Australian-based resources company that is creating value from a portfolio of early
to advanced stage gold and copper projects in Victoria, Australia. .
Navarre is searching for gold deposits in the partially covered extension of a corridor of rocks that host the Stawell (~5 million
ounce) and Ararat (~1 million ounce) goldfields. The discovery of outcropping gold at Irvine and Benno prospects is a prime
focus for the Company in 2015. These are located only 15km south of the operating Stawell Gold Mine which is owned by
Navarre’s largest shareholder and leading Victorian gold producer, Newmarket Gold Inc.
The Company is also targeting large VMS and porphyry- copper and gold deposits. The Western Victoria Copper Project
captures multiple, largely untested targets in 130km of western Victoria’s Miga Arc volcanics. Grassroots exploration of the
Company’s extensive exploration permits is at an early stage and more than 50 new targets remain to be thoroughly drill
tested.
At the high-grade Tandarra prospect within the North Bendigo Goldfield of central Victoria, exploration work is targeting the
next generation of gold deposits under shallow cover 40kms north of the 22 million ounce Bendigo Goldfield. Under a farmout agreement, Catalyst Metals Limited is earning a 51% equity interest in Tandarra by spending $3 million over four years by
advancing the project towards mineral resource status.
Navarre has an experienced leadership team with 120 combined years of exploration, mining and finance industry experience
with a proven track-record of discovery and project development.
For further information, please visit www.navarre.com.au or contact:
Geoff McDermott
Managing Director
E: info@navarre.com.au
T: +61 (0)3 5358 8625
Competent Person Declaration
The information in this release that relates to Exploration Targets, Exploration Results, Mineral Resources or Ore Reserves is
based on information compiled by Wessley Edgar, who is a Member of The Australasian Institute of Mining and Metallurgy
and who is Exploration Manager of Navarre Minerals Limited. Mr Edgar has sufficient experience which is relevant to the
style of mineralisation and type of deposit under consideration, and to the activity which he is undertaking, to qualify as a
Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves’. Mr Edgar consents to the inclusion in the release of the matters based on his information in the
form and context in which it appears.
Forward-Looking Statements
This announcement contains “forward-looking statements” within the meaning of securities laws of applicable jurisdictions.
Forward-looking statements can generally be identified by the use of forward-looking words such as “may”, “will”, “expect”,
“intend”, “plan”, “estimate”, “anticipate”, “believe”, “continue”, “objectives”, “outlook”, “guidance” or other similar words,
and include statements regarding certain plans, strategies and objectives of management and expected financial
performance. These forward-looking statements involve known and unknown risks, uncertainties and other factors, many of
which are outside the control of Navarre and any of its officers, employees, agents or associates. Actual results, performance
or achievements may vary materially from any projections and forward-looking statements and the assumptions on which
those statements are based. Exploration potential is conceptual in nature, there has been insufficient exploration to define a
Mineral Resource and it is uncertain if further exploration will result in the determination of a Mineral Resource. Readers are
cautioned not to place undue reliance on forward-looking statements and Navarre assumes no obligation to update such
information.
Navarre Minerals Limited | ABN 66 125 140 105
40 - 44 Wimmera Street | PO Box 385 | Stawell VIC 3380 Australia
t +61 3 5358 8625
e info@navarre.com.au | w navarre.com.au
Navarre Minerals Limited ASX Announcement
P a g e | 11
Table 1: Irvine and Benno prospects rock chip sample locations & gold assay results for samples >0.1 g/t
Sample_ID
MGA_East
MGA_North
Au
g/t
As
ppm
Cr
ppm
G463
G466
G474
G475
G476
G481
G482
G484
G487
G495
664596.47
664514.05
664979.14
664998.44
665003.51
664876.87
664914.07
664767.35
664589.81
664693.45
5882047.27
5882064.34
5882909.07
5883017.39
5883102.25
5882354.41
5882303.32
5882287.16
5882107.34
5882413.69
0.23
0.11
0.18
0.19
0.12
0.14
4.65
1.71
0.80
0.26
341
398
40
40
127
73
3450
1285
827
398
170
51
54
54
35
17
468
229
130
52
G498
664690.93
5882972.88
0.55
224
29
G500
G505
G510
G514
G517
G518
664772.26
664637.89
664763.73
664384.84
664830.32
664831.55
5881702.56
5881751.04
5881685.21
5881256.33
5881442.21
5881483.43
0.58
0.11
1.98
3.12
0.30
3.34
208
163
238
97
88
273
57
25
33
26
36
14
G526
665529.57
5883550.50
1.03
315
58
G526a
665529.57
5883550.50
0.86
276
89
G529
G530
G531
G532
G533
G534
G535
G536
G540
G579
G581
G585
G590
G591
G592
G597
664897.69
664908.43
664908.99
664909.43
664913.48
664923.53
664937.41
664938.02
664848.05
664997.25
664986.46
665008.83
664946.48
665094.34
665071.02
664922.08
5882299.25
5882298.99
5882299.53
5882300.23
5882303.16
5882310.03
5882307.42
5882307.74
5883086.82
5882914.63
5882865.14
5882812.51
5882387.66
5882350.97
5882339.24
5882080.55
0.16
8.33
1.16
1.69
3.14
3.34
2.41
0.88
0.19
0.55
0.16
0.18
0.11
2.70
4.90
0.28
43
3710
1685
1545
3170
687
656
675
636
133
32
50
27
18
107
9
14
412
114
76
313
74
78
85
56
160
27
63
48
24
20
26
Description
Foliated Mn-Ironstone
Ironstone
Quartzite (sediment), laminated, limonite staining
Mn Ironstone
Mn-Fe (limonite) stained sandstone
Mn-Fe-Quartz stone
Oxidised hematite-limonite rock after basalt/ volcanogenics?
Foliated Mn-Ironstone
Mn-Fe sandstone
Mn-Ironstone
Quartz-limonite Ironstone / foliated meta-siltstone (mine
schist)
Quartzite sediment with hematite-limonite & sulphide casts
Manganese-quartz Ironstone
Foliated quartzite sediment with limonite staining
Quartzite sediment with limonite & sulphide casts
Quartzite sediment with hematite staining
Quartzite sediment with limonite staining & sulphide casts
Cambrian brown siltstone, brittle fracture infill cream silica –
Benno’s Prospect
Cambrian brown siltstone, brittle fracture infill cream silica–
Benno’s Prospect
Quartz vein
Quartz vein
Quartz vein
Quartz vein
Quartz vein
Quartz vein
Fe-Quartz vein
Fe-Quartz vein
Foliated Ironstone
Quartzite sediment with limonite staining
Quartzite sediment with quartz foliations
Quartzite sediment with minor limonite
Quartzite sediment with hematite staining
Laminated quartzite sediment
Quartzite sediment with sulphide pits
Laminated quartzite sediment with hematite staining
Navarre Minerals Limited | ABN 66 125 140 105
40 - 44 Wimmera Street | PO Box 385 | Stawell VIC 3380 Australia
t +61 3 5358 8625
e info@navarre.com.au | w navarre.com.au
Share your feedback
Discover